Section: 9

Date: 12/03/2015

Edition 1, Revision: 0

Page: 2 of 2

K.

Inspection and monitoring is done of below mentioned material:

1.

All Forms used at plant for precast concrete products

2.

Application of release agent on Form

3.

Selection of appropriate steel reinforcement

4.

Placement of the steel reinforcement in the forms during concrete pouring

5.

Checking of proper coverage with appropriate size of spacer used

6.

Leveling of concrete

7.

Cleaning, curing and stripping of precast concrete product

8.

Finish precast product

L.

Updating daily of production progress sheet of inspection - as mentioned in QC Section 6.

M.

As per CSA and ASTM standards, all precast concrete products are repairable. At Diamond we

have categorized into major (Not to be repaired) and minor (To be repaired) defect. For any

defect is found, QC inspectors will inspect the defect immediately create NCR as per Exhibit #19

and defect is recorded and categorized as Major or Minor defect. Major defects are rejected

written as NOT TOBE REPAIRED and products having Minor defects are put on hold as per

Exhibit # 20 until repaired and again inspected.

N.

Finished and inspected product are then labelled with Company Logo, Contact Information,

Manufacturing Date, Weight of products and Product ID # as described in Label Exhibit # 2.

Separate CSA label will be applied to each product. (painted by stencil)

O.

Supplies are given from the oldest date manufactured.

P.

Products are stored in yard to the specified identified position.

PRECAST CONCRETE