B.3.5 Joint materials

B.3.5.1

Joint materials between precast concrete elements and adjacent materials shall not be included in the

precast concrete work.

Note:

This work is generally more efficiently carried out by the subsequent trade installing such adjacent materials.

B.3.5.2

The contract drawings and project specifications shall clearly show the responsibility for the supply and

installation of materials at the joints between precast concrete elements and other materials installed

before the precast installation (e.g., cast-in-place structures and steel members).

B.4 Holes and openings

B.4.1

All openings for services and equipment, with their approximate size and location shown on the contract

drawings, and the same holes subsequently detailed with respect to size and location by the trades

requiring the openings, shall be coordinated by the general contractor and noted on the first issue of the

precast manufacturer’s shop drawings. The openings shall be provided by the precast manufacturer,

except as specified in

Clause B.4.2

.

Note:

Sizes and locations of openings should be adjusted to avoid major reinforcing bars, prestressing tendons, supporting

beams, and double Tee legs.

B.4.2

Holes of small diameter (80 mm or less) or holes for fastenings intended to carry less than 500 N shall be

made at the site by the trade requiring the opening, in locations reviewed by the precast manufacturer.

Note:

Holes made by other trades should not be located in areas of structural importance (e.g., reinforcement and tendon

locations).

B.4.3

The procedures specified in

Clause B.4.1

shall be followed whether the precast manufacturer provides

openings at the plant or elects to cut and drill openings on site.

B.4.4

Openings requested after review of the shop drawings and production of precast elements shall be cut

only if the openings can be structurally accommodated.

Notes:

(1)

These modifications should be carried out by the precast manufacturer, which will have the equipment and expertise

needed to cut new openings.

(2)

Holes in architectural wall panels for other trades should be made at the manufacturing plant and consequently should

be detailed and located on the contract drawings.

B.5 Roof and floor fill

B.5.1

If roof or floor slab joints have grout keys that form part of the slab design, the grouting shall be executed

by the precast installer and the areas made ready for roofing or floor fill as necessary.

Licensed for/Autorisé à Jed Friesen Sold by/vendu par CSA on/le June/18/2015.

~Single user license only. Storage, distribution or use on network prohibited. Permis d'utilisateur simple seulement.

Le stockage, la distribution ou l'utilisation sur le réseau est interdit.