MASTER CONTRACT:

260881

REPORT:

2784857

PROJECT:

2784857

Page No:

6

Date Issued:

March 24, 2015

DQD 507.10 Rev. 2013-06-19

e) Substitution of a “Certified” and/or “Listed” component with a component that is “Recognized” or

“Accepted” is not permitted without evaluation and report updating.

Group D1, Standard Precast Concrete Drainage Products

This group includes the following products: box units with span greater than 3m, open footing (3-sided) precast

units with flat top slab or arch top – all sizes, Precast components for culverts such as wing walls, retaining walls,

headwalls, parapet walls, strip footings, pile caps, load distribution slabs, etc., rectangular manholes and chambers

– all sizes

The evaluation was conducted on representative samples of produced products, a full set of drawings of these

prototype elements that were the subject of CSA site evaluation is kept on file along with the plant Quality

Control Manual. Evaluations for compliance were conducted at different stages of production and included the

following:

1) Plant quality control manual;

2) Shop drawings;

3) Mix proportions;

4) Forms;

5) Fabrication and placement of reinforcement and hardware;

6) Pre-pour inspection;

7) Placing of concrete;

8) Protection and curing; (conventional curing)

9) Concrete quality;

10) Post-pour inspection;

11) Stripping and handling; and

12) Storage, transportation and installation

Group S (Standard Products)

This group includes the following products: plain or reinforced concrete elements, without architectural finishes

that are not included in Groups A, B, BA, C, or CA and are required to be manufactured in accordance with the

provisions of CSA A23.4 Standard.

Products in Group S are often manufactured for a particular application in custom built forms on demand or kept

in inventory.

The evaluation was conducted on representative samples of produced products, a full set of drawings of these

prototype elements that were the subject of CSA site evaluation is kept on file along with the plant Quality

Control Manual. Evaluations for compliance were conducted at different stages of production and included the

following:

1) Plant quality control manual;

2) Shop drawings;

3) Mix proportions;

4) Forms;

5) Fabrication and placement of reinforcement and hardware;

6) Pre-pour inspection;

7) Placing of concrete;

8) Protection and curing; (conventional curing)

9) Concrete quality;

10) Post-pour inspection;

11) Stripping and handling; and

12) Storage, transportation and installation

PRECAST CONCRETE

Property of